Hunter Power Project · NSW
Hunter Power Project
Symal Infrastructure — Hunter Power Project (UGL for Snowy Hydro)
Kurri Kurri NSW · Jan 2024 – May 2024

A full Sorco crew mobilised interstate to form, reinforce and pour the power station structures for a 660 MW dual-fuel gas plant.
Formwork, reinforcement and concrete placement to power station structures, including columns, footings and plinths
Temporary works design and certification where required
Installation of free-issued reinforcement, cast-in plates, embedments and services
Blinding and structural concrete placement, compaction, finishing and curing to thermal requirements
Patching and crack repair
Engineering and project management support to the Symal and UGL delivery teams
Crew travel, rostering and living-away arrangements managed by Sorco