North East Link

Watermain Diversion Slabs

SPARK — North East Link

Melbourne VIC · Aug 2024 – Mar 2025

1,200 m²

1,200 m²

Formwork installed up to 4,500mm high

Formwork installed up to 4,500mm high

3,250 m³

3,250 m³

Concrete placed

Concrete placed

1,460 m³

1,460 m³

Single pour completed in 12 hrs

Single pour completed in 12 hrs

ZERO

ZERO

Safety incidents / injuries

Safety incidents / injuries

Diversion slabs with formwork up to 4.5 m high, including a 1,460 m³ pour completed in a single 12-hour shift.

  • Blinding placement, install of sacrificial ply

  • Supply & install of single & double-sided formwork up to 4,500mm high

  • 1,460 m³ concrete placed in a single 12-hour pour

Specialist concrete construction for Australia’s major infrastructure.

Contact

14-16 MacBeth St, Braeside VIC 3195

(03) 9017 3128

admin@sorco.com.au

Sorco acknowledges the Traditional Owners of the lands on which we work, and pays respect to Elders past and present.

© Sorco Group Pty Ltd 2026. All rights reserved.

Privacy policy

LinkedIn

Specialist concrete construction for Australia’s major infrastructure.

Contact

14-16 MacBeth St, Braeside VIC 3195

(03) 9017 3128

admin@sorco.com.au

Sorco acknowledges the Traditional Owners of the lands on which we work, and pays respect to Elders past and present.

© Sorco Group Pty Ltd 2026. All rights reserved.

Privacy policy

LinkedIn

Specialist concrete construction for Australia’s major infrastructure.

Contact

14-16 MacBeth St, Braeside VIC 3195

(03) 9017 3128

admin@sorco.com.au

Sorco acknowledges the Traditional Owners of the lands on which we work, and pays respect to Elders past and present.

© Sorco Group Pty Ltd 2026. All rights reserved.

Privacy policy

LinkedIn