North East Link
Bridge 104, Gantries & Barriers
SPARK — North East Link
Melbourne VIC · 2025 – 2027

Precast install, abutments and deck slab for Bridge 104, plus over 1,500 lm of precast performance barrier and gantry footings.
Precast prep & install
Form, reinforce & pour abutments
Form, reinforce & pour deck slab, kerbs, upstands & footpath infills
Precast performance barrier install & stitch pours
Over 1,500 lm of precast performance barrier install & stitch pour
Excavation & pile breakback to gantry footings
Form, reinforce & pour gantry footings
Form, reinforce & pour retaining wall footings & stitch pours, including casting early propping system
Precast install for retaining wall panels