North East Link
MHM Box Base Slabs & SB Ramp Roof Slab
SPARK — North East Link
Melbourne VIC · 2025 – 2026

28 base slab pours of up to 2,000 m³, internal core walls up to 18 m high, and the southbound ramp roof slab.
28 base slab pours ranging from 500 m³ to 2,000 m³
Formwork install to all base slabs, avg. 2,000mm deep
Install pits & drainage to base slabs
4,000 m² of formwork to internal core walls up to 18 m high
Precast install & grouting
CFC sheet install between planks
Form & pour 1,800mm high stitch pours to edge of precast
Form & pour topping slab & delay strips